N.J.S.A. 48:3-113

Standby charge.

48:3-113 Standby charge. 4. a. Upon request to an electric public utility, electric power supplier, or basic generation service provider for standby power by a facility that supplies power to an end-use customer pursuant to section 3 of P.L.2017, c.357 (C.48:3-112) or the end-use customer of that power, the electric public utility, electric power supplier, or basic generation provider, as applicable, shall impose and assess a standby charge. b. The Board of Public Utilities shall, within 120 days after the effective date of P.L.2017, c.357 (C.48:3-110 et seq.), establish criteria for an electric public utility, electric power supplier, or basic generation provider to assess and impose a standby charge. L.2017, c.357, s.4.

External source: View on Justia →

This is the verbatim text of N.J.S.A. 48:3-113, retrieved from the New Jersey Legislature's public statute corpus. Statutes are amended periodically — for the most current version, check the external source link above. Kyzer is not a law firm and this page is not legal advice.