N.J.S.A. 48:13-13

Time of commencement and completion of sewerage system

48:13-13. Time of commencement and completion of sewerage system Every sewerage company organized under the laws of this State shall commence the construction of the proposed system of sewerage within 6 months from the date of its organization, and shall complete the same within 3 years from the date of commencement. The conditions annexed to the consent of the corporate authorities may designate a shorter period for the completion of such works. Amended by L.1962, c. 198, s. 162.

External source: View on Justia →

This is the verbatim text of N.J.S.A. 48:13-13, retrieved from the New Jersey Legislature's public statute corpus. Statutes are amended periodically — for the most current version, check the external source link above. Kyzer is not a law firm and this page is not legal advice.