N.J.S.A. 18A:64-77

Deduction for costs of completion.

18A:64-77 Deduction for costs of completion. 26. All specifications for the doing of any construction work for a State college shall fix the date before which the work shall be completed, or the number of working days to be allowed for its completion, and every contract shall contain a provision that if the construction work is not completed by the date fixed for completion or in the number of days allowed for completion, as set forth in the specifications, there shall be a deduction from the contract price for any moneys paid by the college to other contractors for the completion of the project. This requirement shall not preclude the State college from seeking liquidated damages or other remedies. L.1986,c.43,s.26; amended 2005, c.369, s.14.

External source: View on Justia →

This is the verbatim text of N.J.S.A. 18A:64-77, retrieved from the New Jersey Legislature's public statute corpus. Statutes are amended periodically — for the most current version, check the external source link above. Kyzer is not a law firm and this page is not legal advice.

N.J.S.A. 18A:64-77 — Deduction for costs of completion. | Kyzer